The following describes our recent, current and planned operations.
2021
Road building and logging operations will be active at the following sites:
Road Construction
East Salloompt, August – October, 1.5 km of new road being built
West Nookliklonnik, – on hold to 2022, 1 km old road reactivated, 1 km new
Logging
Noomst: April – May
East Salloompt: May – October
North Bentinck Forest Road (at harbour): Hauling April – October.
Planting
May: Noomst
2020
Road building and logging operations were active at the following sites:
Road Construction
Noomst, 1 km of new road built
Logging
West Nusatsum: logging completed
Noomst: mostly done, minor clean-up in 2021
Planting
May: Nusatsum, East Salloompt, Noomst